Posted 2/1/09
Mission Center Construction -
The construction has started and the trailers have been moved. During the construction of the New Mission Center, please be cautious while walking and driving around the Parish.  Heavy equipment will be moving about the area until construction has been completed.

Posted 12/08/08 --We have made good progress with the Planning & Building Department. There has been a meeting and many telephone conversations to resolve the outstanding issues. We are optimistic and hopeful that by the time you read this update that the Building Permit will have been issued. Please continue to pray for a successful conclusion for the Design /Permit process and the startup of the construction process.

Posted 11/17 -- Mission Center Update
We are waiting for the Building Department to complete their review of our last submission. The Plan Check Engineer has estimated that she will complete the review by November 24. Please continue to pray for a successful conclusion to the Design /Permit process and a successful startup of the construction process.

Posted: 10/11/08 -- Mission Center Update
The Mission Center Project is in the final phase of the Design/ Building Permit Process. The final design drawings were submitted to the Building Department on September 12. We have asked the Building Department Plan Checker to release the necessary permits that will allow us to do the underground utilities work, to build a 3 foot retaining wall which is located by the sidewalk on the north side of the building and to build the foundation and slab for the building. We anticipate that we will have the necessary permits by the time you are reading this article. You should begin to see activity in the construction area at the end of this coming week or beginning of next week.

Posted: 10/26/08 -- Mission Center Update-Jim Koepf
The Design Team is working hard to have our responses ready to submit to the Building Department by Friday October 24. After the review of our responses by the Plan Check Engineer I estimate that we should be able to have the Building Permit by Nov 7.  Construction will begin soon after this date. Please pray for the successful conclusion for the Design/Permit process.


Performance to Goal$1.9M is the goal!
As of July 28, the Mission Center Appeal total is $1,881,472 and 536 families have participated.
As of June 27, $1,859,847.00
As of June15 $1,838,657.00
As of June 8 $1,818,152.00
As of June 1 $1,764,516.00
As of May 26 $1,693,025.00
As of May 19 $1,632,295.00
As of May 26 $1,693,025.00 
As of June 1 $1,764,516.00


For more, view our Mission Campaign brochure  

If you have questions about our new Mission Center, contact Father John, Father Loi, Willy Agbayani, John Toole or any Parish Council member or call the parish center at 408-223-1562.

 If you need a free reader, click here.

 

 
 

 

 

Our Need:

 
  • Relocate offices for priests and staff when forced to eliminate trailers
  • Creatively accommodate growth and overcrowding
  • Meet the needs of youth, teens, and adults of all ages who choose to worship at St. Francis
  • Meeting these needs will deepen our relationship with Christ and each other
  •   Our Opportunity:
     
  • Expand our worship space with a seat for everyone - from 450 seats up to 1000
  • Create a place for Catholic hospitality after every Mass
  • Enable us to create and manage programs that change lives
  • Begin operation of our Mission Center by Jan 2009
  •   Why Now:
     
  • City requires that our trailers must be removed immediately
  • Plan avoids escalating costs, saving resources in the long term
  • Many Masses have standing room only; on Christmas/Easter, crowds must stand outside
  • Able to use the Mission Center in Jan 09, which completes Phase II of the approved Master Plan
  •  

     
      Financials:
     
  • Total cost is $1.91M
  • Parish has $1.58M from --

    =Vince & Colleen Cortese lead gift
    =Several generous major donors
    =Parish funds for facilities


  • =Need to raise $330K to complete Mission Center; proceeding with exterior construction contract
    =All funds are need by Nov 2008

      Timetable:
     

    May 4:  Appeals at Mass
    May:  Gift envelopes returned
    Jun 1: Final in-pew requests
    Jun 29: Groundbreaking (See ceremony slideshow)
    Nov 30: All gifts collected
    Jan 31 (2009): Center opens
    Mar 31 (2008): Dedication

       
     

     

            